PMP Sample Questions
- Which of the following it the logical flow of any project?
- Planning, Initiating, Executing, Controlling, Closing
- Initiating, Planning, Controlling, Executing, Closing
- Planning, Initiating, Executing, Controlling, Closing
- Initiating, Planning, Executing, Controlling, Closing
Answer: D
- In which phase of a project would you estimate activity duration and resources?
- Initiating
- Executing
- Planning
- Controlling
Answer: C
- Which of the following according to the PMBOK is described as, “a category or rank given to entities having the same functional use but different technical characteristics?”
- Grade
- Quality
- Flow design
- Benchmark
Answer: A
- Which of the following is another name for an Ishikawa diagram?
- Cause and Effect Diagram
- Bell Curve
- Pareto Diagram
- Trend Analysis
Answer: A
- Refinements are considered updates for the ____.
Answer: C
- The acronym CPPC stands for?
- Cost Plus Percentage of Control
- Cost Plus Percentage of Contract
- Cost Plus Percentage of Cost
- Cost Plus Plus Cost
Answer: A
- Which of the following is not considered part of Maslow’s Hierarchy of Needs?
- Social needs
- Safety
- Motivation
- Self-actualization
Answer: C
- Parento diagrams work on the ___ rule.
Answer: C
- Which of the following is a key aspect of quality control?
- Limited in scope
- Minimal planning resources
- Generic cost controls
- Project wide focus
Answer: D
- The creator of the project charter is identified as the ______.
- Project manager
- Outside senior manager
- Internal control expert
- Quality control expert
Answer: B
« Previous || Next »
PMP Sample Question Number :
1-10|
11-20|
21-30|
31-40|
41-50|
51-60|
61-70|
71-80|
81-90|
91-100|
101-110|
111-120|
121-130|
131-140|
141-150|
151-160
|
|